Friday 22 February 2008

here we go again...

Yesterday was the last day of the lunar new year period. Workers has already started work last Tuesday. Things are moving fast. By last night, the electrical wiring are all done up.

MBR ceiling lights and fan wiring

Kitchen wiring for cooker, hood and oven

Spotlights wiring for display cabinet

The false wall between the MBR and bedroom & Kitchen sliding door are up too.


Low wall btw MBR and bedroom

Top false wall for kitchen sliding door

View from inside the kitchen

Tuesday 5 February 2008

Break for the festive period

The renovation shall break for the Lunar New Year period. Here wishing all readers good health and wealth for the new year.

鼠年行大运,钞票鼠不完


Gong Xi Gong Xi

Sunday 3 February 2008

Partition, Air-con trucking and Gas... con't

Gas water heater arrived
Heater wall mounted

Gas point for cooker and dryer

Partition, Air-con trucking and Gas... con't

Trucking running from MBR

Across into BR3


Trucking in BR3

and BR2

Partition, Air-con trucking and Gas...

It was hectic last Friday, 1st Feb. Three groups of people were at work, one for constructing the partition wall for the closet at the bedrooms, another was the air-con installation guys laying the piping, electrical wires, etc for the air-conditioners, last was the citigas guys fixing the gas water heater and gas piping.

First up, pictures of the partition for the closets.

MBR closet1 partition - raw

MBR closet1 partition - done up

MBR closet2 partition - raw

MBR closet2 partition - done up

BR3 closet partition - raw
BR3 closet partition - done up